Given the network shown in Figure 11-1, assume that the completion of activity C is delayed by four days. What changes will take place?

A) The critical path will change to: A-C-B-D-E-F-H.
B) Activity F will be delayed by four days.
C) Activity E will be delayed by four days.
D) Activity G will be delayed by four days.
E) None of the above


E

Business

You might also like to view...

Under the ______________style, the leader makes all the decisions with little input from the team.

a. laissez-faire b. authoritative c. democratic d. none of the above

Business

A sale takes place when title to the goods transfers to the buyer

Indicate whether the statement is true or false

Business

During the correct or reinforce step of the control systems process, after performance is complete and it is too late to take corrective action to meet the standard, the appropriate corrective actions are to do all of the following, EXCEPT ______.

a. analyzing why the standards were not met b. using the information to develop preliminary control c. developing sophisticated rework controls and overseeing their immediate implementation d. giving feedback so as to take corrective action necessary to meet the objective/standard next time

Business

What are the pros and cons of a franchising agreement for global expansion?

What will be an ideal response?

Business