There are 50 units in inventory at the start of week 1 for this company, which runs a lot-for-lot MRP system. There is a one week lead time for all shipping and production quantities regardless of volume
What are the quantities of the planned order releases for this item for the first six weeks?
1 2 3 4 5 6 7 8
Gross Requirements 50 20 30 40
Scheduled receipts
Projected ending Inventory
Net Requirements
Planned Receipts
Planned Orders
A) 20, 30, 0, 40, 20, 0
B) 35, 0, 60, 0, 0, 0
C) 5, 30, 0, 40, 20, 0
D) 35, 0, 0, 40, 20, 0
Answer: A
You might also like to view...
An overall management objective is to:
a. minimize the number of sales transactions b. minimize the total amount of accounts receivable c. minimize the time from the beginning of the selling process to the end of the cash collections process d. maximize the amount of float
What are the six practical principles for business offered by the Catholic Church?
What will be an ideal response?
____________________ is the allocation of the cost of a tangible, long-term asset over its useful life
Fill in the blank(s) with correct word
The public pathway to raise equity capital outside of its home market includes the following EXCEPT:
A) Euroequity issue. B) Strategic Partner/Alliance. C) shares sold to a specific market or exchange. D) seasoned offering.