When reducing project duration, the duration for a project that is optimal is at the point where

A. Direct costs equal indirect costs.
B. Indirect costs are the lowest.
C. The project changes from time-constrained to resource-constrained.
D. Direct costs are the lowest.
E. Total project costs are the lowest.


Answer: E

Business

You might also like to view...

Which of the following is a characteristic of BigData?

A. It is typically only text-based. B. It is unstructured. C. It is usually around 100 gigabytes in size. D. It is generated rapidly. E. It is processed using traditional techniques.

Business

It is possible for two companies to have the same financial performance, but their financial

statements can be different, depending on how and when the managers choose to report certain transactions. Indicate whether the statement is true or false

Business

Paul and Diana are married and own a home. Both of their names are on the mortgage. This is an example of A)?a tenancy in kind

B)?a tenancy at will. C)?a concurrent estate. D)?a share estate.

Business

Cavanaugh Co. has provided the following information for last year: Gallons input ??? @$20/gallonLabor costs 5,000 @$20/hrOverhead costs$110,000   Gallons finished 8,000 @selling price of $55/gallonTotal factor productivity 1.0732   The total number of gallons input (rounded) is:

A. 200,000 gallons. B. 10,000 gallons. C. 7,450 gallons. D. 8,600 gallons.

Business