One way to determine the duration of each activity in a project with a reasonable degree of accuracy is ______.
A. deterministic estimation
B. qualitative estimation
C. optimistic estimation
D. pessimistic estimation
A. deterministic estimation
You might also like to view...
When no-par common stock with a stated value is issued for cash, the common stock account is credited for an amount equal to the cash proceeds
a. True b. False Indicate whether the statement is true or false
Paid advertising offers all of these guaranteed benefits EXCEPT ________
A) control over content B) location where the content will appear C) credibility of the ad D) frequency of times the ad is run
A manufacturing company is expected to complete a task in 45 minutes. During a recent accounting period, 3,200 completed units were produced, resulting in the following labor variances: Labor rate variance: $520 favorableLabor efficiency variance: $2,800 unfavorableThe standard labor rate is $14 per hour.Required: Calculate (1) the standard hours allowed for the work performed, (2) the actual hours worked, and (3) the actual wage rate.
What will be an ideal response?
What skill frees the imagination, opens up the mind to a wealth of opportunities and possibilities, and helps foster innovation?
a. skill of creativity b. skill of reflection c. skill of experimentation d. skill of play