A project has the precedence requirements and activity durations shown in the table. After he draws the network, the project manager decides that activities E and F can be represented by a hammock activity
What are the duration and the early start time associated with this hammock activity?
Time Predecessor
A 7
B 8 A
C 13 B
D 8 C
E 7 A
F 6 E
G 6 A
H 11 G
I 12 H
J 14 D, F, I
A) 13, 36
B) 7, 0
C) 13, 7
D) 7, 14
C
You might also like to view...
The principle of normal trade relations (most-favored-nation) treatment was established with the passage of the
a. Fordney-McCumber Act of 1922. b. Smoot-Hawley Act of 1930. c. Reciprocal Trade Agreements Act of 1934. d. Trade Act of 1974.
Which of the following costs would not be included in factory overhead in the manufacture of a student's desk?
a. The oil used to maintain the machinery. b. The salary of the supervisor of the Assembly department. c. The wood used to form the top of the desk. d. The wages of personnel who perform inspections of incoming materials.
Good-news or neutral-news messages follow a(n) _____.?
A) ?indirect sequence B) ?passive sequence C) ?inductive sequence D) ?deductive sequence
Use of the Internet for recruiting is
A. popular with job seekers, but not recruiters. B. popular with recruiters, but not job seekers. C. cheaper and easier, but less effective than other methods. D. the most commonly used search tactic by job seekers and recruiters.