What organizational disciplines are required in order for an organization to successfully run a material requirements planning system?
What will be an ideal response?
Answer: An MRP system needs accurate inputs in the form of a master schedule, bill of materials, inventory records, and planning lead times. An organization must have the organizational discipline to maintain inventory records as they use materials, receive orders from vendors, and ship finished goods. The organization must begin with accurate BOM data and update the data as product configurations change. The organization must have open lines of communication with their customers and vendors in order to verify that lead time and order quantity information is accurate and up-to-date.
You might also like to view...
Your bank offers a 10-year certificate of deposit (CD) that pays 6.5% interest, compounded annually. If you invest $2,000 in the CD, how much will you have when it matures?
A. $3,754.27 B. $3,941.99 C. $4,139.09 D. $4,346.04 E. $4,563.34
Define the term ethical dilemma. Give an example from your life when you faced an ethical dilemma.
What will be an ideal response?
During 2010, Heckart Corporation had sales of $250,000, net income of $25,000, average total assets of $350,000, dividend payments of $17,500, net cash flows from operating activities of $26,000, purchases of plant assets of $37,500, and sales of plant assets of $45,000 . Cash flows to assets equals (Round amounts to one decimal place)
a. 13.0 percent. b. 10.4 percent. c. 8.7 percent. d. 7.4 percent.
A researcher should make notes for references and quotations, but not for paraph-rases
Indicate whether the statement is true or false