Project managers must often face the challenge of compressing the project schedule. All of the following actions can be taken to reduce the duration of the critical path EXCEPT:
a. Reduce the project scope and /or quality.
b. Overlap sequential activities using finish-to-finish, start-to-start, or start-to-finish relationships.
c. Use the float in critical path activities
d. Partially overlap sequential activities by using time leads.
C
You might also like to view...
A table is in second normal form when it is
a. free of repeating group data b. free of transitive dependencies c. free of partial dependencies d. free of insert anomalies e. none of the above
What Strategic issues particular to the enterprise(s) and context described
What will be an ideal response?
In establishing a dividend policy, a firm should retain funds for investment in projects yielding higher returns than the owners could obtain from external investments of equal risk
Indicate whether the statement is true or false
The type of pay raise in which the employee can receive the entire amount of the increase at the beginning of the year is called a(n)
A. incentive payment. B. lump-sum salary increase. C. commission salary increase. D. gain-sharing salary increase. E. percentage-of-salary payment.