If the most optimistic time for completing an activity is 3, the most likely time is 6, and the most pessimistic time is 9, then the estimated time for the activity is ______.
A. 6
B. 3
C. 8
D. 21
A. 6
You might also like to view...
When epistemic motivation is high, people analyze situations, weigh arguments, and solve problems through effortful thinking; in contrast, when epistemic motivation is low, people are more likely to form quick impressions and make snap judgments based on well-learned rules and heuristics.
Answer the following statement true (T) or false (F)
The mission of the Fair Labor Association (FLA) is to ______.
a. assess and certify that certain suppliers treat their workers ethically b. force developing country governments to crack down on sweatshops c. encourage major corporations to bring work back to developed nations where workers are treated ethically d. prosecute Western businesses for employing sweatshop labor through third parties
Earnings per share is a measure of
a. cash income earned by the common shareholder. b. profitability. c. the financial viability of a firm. d. the amount of dividends that will be paid by the firm. e. how much an investor would be willing to pay for a share of common stock.
Market pricing refers to:
A. the point where supply and demand curves cross B. adjusting the price of products according to the prices of competitors C. combining jobs into a broader market band D. relying on external market rates to set the internal pay structure E. paying rates that reflect product market conditions