Answer the following statements true (T) or false (F)
1. The length of the arrows in a PERT diagram has a direct relationship with the duration of the activity.
2. The critical path is defined as the most expensive path.
3. PERT diagrams occasionally need to use dummy activities to preserve the logic.
4. An advantage of PERT diagrams is the easy determination of slack time.
5. A PERT diagram does not allow for easy identification of the critical path and thus critical activities.
1. FALSE
2. FALSE
3. TRUE
4. TRUE
5. FALSE
You might also like to view...
INPUT car_manufacturer
What will be an ideal response?
When the Split Table button is clicked, a blank paragraph is inserted above the table
Indicate whether the statement is true or false
What are the four parts to every function?
A. An equal sign, the function name, a set of parentheses, and variables B. An equal sign, the function name, a set of brackets, and arguments C. An equal sign, the function name, a set of parentheses, and arguments D. A plus sign, the function name, a set of parentheses, and arguments
A(n) __________ variable is declared inside a module and cannot be accessed by statements that are outside the module.
Fill in the blank(s) with the appropriate word(s).