A(n) ________ calculates how late an activity can start and finish.
Fill in the blank(s) with the appropriate word(s).
backward pass
The backward pass calculates how late an activity can start and finish. It also determines the critical path and how long activities can be delayed without delaying the project.
You might also like to view...
Answer the following statements true (T) or false (F)
An advantage of proportionate consolidation is that the minority interest category does not arise.
A contract can never be enforced against an intoxicated person
Indicate whether the statement is true or false
The origins of mutual funds can be traced back to the mid to late 1800s in ________
A) England and Scotland B) New York City C) Boston D) Germany
For information systems, the role of logical security is to protect the physical assets that support the storage and processing of information
Indicate whether the statement is true or false.