Given the following information for a project, identify the critical path and determine the total completion time of the project

Activity Immediate Processor Activity Time (days)
A - 6
B - 8
C A, B 5
D B 4
E C 7
F C, D 3
G D 6
H E, F, G 5


Answer: Critical path = BCEH. Project completion time = 25 days.

Activity ES EF LS LF Slack CP
A 0 6 2 8 2 No
B 0 8 0 8 0 Yes
C 8 13 8 13 0 Yes
D 8 12 10 14 2 No
E 13 20 13 20 0 Yes
F 13 16 17 20 4 No
G 12 18 14 20 2 No
H 20 25 20 25 0 Yes

CP = Critical Path

Business

You might also like to view...

How is income from operations determined?

a. By subtracting the total operating expenses from gross profit. b. By subtracting the total operating expenses from sales c. By subtracting the cost of goods sold from sales. d. By subtracting selling expenses from operating revenues

Business

Back Company sold merchandise on credit. Its gross profit ratio is 23%. The effect of this transaction is that the

a. earnings per share decreased b. current ratio was unchanged c. debt-to-equity ratio increased d. earnings per share increased

Business

Which of the following is provided in a typical chart of accounts?

A) Account balance B) Account number C) Dates of transactions D) Transaction amounts

Business

The reserved quantity will be affected by the difference in margin between the spot market and the bulk sale, but not the distribution of demand from the spot market

Indicate whether the statement is true or false.

Business