Which of the following is true of a GMP contract?

a. GMP is the same as a lump sum bid
b. The contractor passes all costs to the owner up to a predetermined maximum
c. The owner assumes all project risk
d. The construction manager assumes all project risk
e. None of the above


B

Trades & Technology

You might also like to view...

Choose the item in column 2 that best matches each item in column 1.

_____1. Which is a clear and well-defined statement of responsibilities and intended outcomes? _____2. Which are small short-term goals that are part of a larger, more complex, overarching goal? _____3. Which is a repair that does not meet quality standards and must return to the shop for additional repairs before delivery to the customer? A) Expectations B) Subgoals C) Redo

Trades & Technology

Why might a designer or engineer not choose the strongest material to make an automobile body?

What will be an ideal response?

Trades & Technology

Every work order should include the vehicle identification number

A) True B) False

Trades & Technology

____ integrated circuits are constructed in the same manner as transistors but include a few additional steps.

A. Thick-film B. Thin-film C. Monolithic D. Hybrid

Trades & Technology