Your company is considering submitting a bid on a major project. You determine that the expected completion time is 100 weeks and the standard deviation is 10 weeks. It is assumed that the normal distribution applies

You wish to set the due date for the project such that there is an 85 percent chance that the project will be finished by this time. What due date should be set?
A) 108.0
B) 110.4
C) 89.6
D) 85.0
E) 100


B

Business

You might also like to view...

What is a characteristic of task analysis?

A. It results in an assessment of employees' readiness for training. B. It is usually conducted along with person analysis. C. It is independent of time constraints or deadlines. D. It helps in determining individuals' needs for training. E. It does not require knowledge of the work environment.

Business

When writing a thank-you letter to the interviewer at a company with high power distance, the writer needs to________

A) only be polite because a thank-you note is nothing more than just a polite gesture B) make her letter less formal than she would if she were writing for an American reader C) keep her letter short and to the point, which is appropriate in a low-context culture D) make it personalized and quirky, so that she will stand out E) make it longer and more formal

Business

A slotting allowance is a form of _____

a. channel conflict b. short-run strategy by a manufacturer c. channel cooperation d. electronic data interchange

Business

Purchasing and manufacturing in high volume to reduce cost per unit is referred to as?

a. Economies of size b. Economies of scope c. Economies of scale d. Economies of setup

Business