Compare bar charts and precedence diagrams in terms of the ease with which activities can be added to the schedule

What will be an ideal response?


It is only on the complex schedules that this issue is a particular concern.
For example, if a schedule consists of 100 activities, it may be difficult to add an
activity to a bar chart and still accurately anticipate the impact of the change on the
entire schedule. With the use of a precedence diagram, the insertion of an activity is a
relatively simple matter. Each activity must generally have at least one predecessor
and at least one successor. With the precedence diagram, the logic is more readily
apparent and incorporating a new activity is a simple matter.

Trades & Technology

You might also like to view...

When fluid is flowing through an orifice the pressures are ________ on each side of the orifice.

A) Unequal B) Pulsing C) Equal D) The same

Trades & Technology

To what accuracy are standard electronic digital calipers capable of reading?

A. 0.0001 inch B. 0.001 inch C. 0.050 inch D. 0.500 inch

Trades & Technology

The ____ can pinpoint causes of combustion chamber leakage.

A. wet compression test B. cranking compression test C. cylinder leakage test D. cranking vacuum test

Trades & Technology

A hammer is used to secure a bearing to a shaft or hold it inside of a housing.

Answer the following statement true (T) or false (F)

Trades & Technology