Who is responsible for developing a risk management strategy?

a. A risk reviewer
b. A technical resource
c. A project champion
d. A risk owner


d. A risk owner
Risks with a high probability of occurrence and a high potentialimpact need to have a risk owner assigned. The risk owner is responsible for developing a risk management strategy and monitoring the project to determine if the risk is about to occur or has occurred.

Computer Science & Information Technology

You might also like to view...

________ the controls makes it easier to format them and keep them aligned

A) Modifying B) Labeling C) Arranging D) Grouping

Computer Science & Information Technology

Which connector type is a 3-row 18- or 24-pin female connector with square holes?

A) S/PDIF B) DVI C) USB D) Thunderbolt

Computer Science & Information Technology

In a fixed charge method, the IT group is regarded as a _____ center, which is a department that is expected to break even or show a profit.

A. profit B. feasibility C. resource  D. volume

Computer Science & Information Technology

By default the first field in a table created using the Blank database command is designated as the primary key field.

a. true b. false

Computer Science & Information Technology