The first two traditional project phases (concept and development) focus on planning, and are often referred to as _____

a. project feasibility b. project acquisition
c. project implementation d. project close-out


a

Business

You might also like to view...

Which one of the following events involves a liability for a business?

a. Loans to be repaid to banks b. Inventories purchased for cash c. Amounts invested by the owners d. Stock sold to the general public

Business

Which of the following is not a technique used to try to train leaders?

a. executive coaching b. listening to motivational speakers c. watching leadership case videos featuring role-models d. scientific experiments

Business

________ rely on gatekeepers for fair and effective functioning of economic markets.

A. Bankers B. District attorneys C. Politicians D. Financial analysts

Business

Kostelnik Corporation uses a job-order costing system with a single plantwide predetermined overhead rate based on machine-hours. The company based its predetermined overhead rate for the current year on total fixed manufacturing overhead cost of $237,000, variable manufacturing overhead of $3.90 per machine-hour, and 30,000 machine-hours. The company has provided the following data concerning Job A496 which was recently completed:Number of units in the job20Total machine-hours80Direct materials$ 500Direct labor cost$ 2,160The total job cost for Job A496 is closest to:

A. $3,104 B. $3,604 C. $1,444 D. $2,660

Business