Assuming that your capital is constrained, which project should you invest in first?

Consider the following list of projects:

Project Investment NPV
A $135,000 $6,000
B 200,000 30,000
C 125,000 20,000
D 150,000 2,000
E 175,000 10,000
F 75,000 10,000
G 80,000 9,000
H 200,000 20,000
I 50,000 4,000

A) Project C
B) Project G
C) Project B
D) Project F


Answer: A

Business

You might also like to view...

The built or natural spaces or settings where interviews take place are known as the ______.

a. interview environment b. interview rapport c. interview affect d. interview process

Business

Explain briefly the purpose of the McCarran Act

What will be an ideal response?

Business

Futures contracts for various commodities have different trading hours depending on the commodity

Indicate whether the statement is true or false.

Business

Which of the following statements about creating constraints is incorrect? a. If you do not provide a name for a constraint, the Oracle 12c server will issue an error message

b. There are two approaches for creating constraints: at the column level or the table level. c. One industry convention is to use the format tablename_columnname_constraint type for the constraint name. d. none of the above

Business