Planned value is ______.
A. the total budget
B. a way to identify the expenditures at any one stage in the project
C. a cost estimate of the budgeted resources scheduled across the project’s life cycle (cumulative baseline)
D. the real budgeted cost, or value, of the work actually performed to date
C. a cost estimate of the budgeted resources scheduled across the project’s life cycle (cumulative baseline)
You might also like to view...
While listening to a lecture, highlighting major points in your notes defeats the purpose of taking notes
Indicate whether the statement is true or false
A model of HRM that focuses more on ensuring that HR strategy fits and is driven by the overall corporate strategy is known as a ______ Model.
a. Systems b. Soft c. Hard d. Planning
Barnett and McKendrick argue that differences in competitive performance within an industry can be attributed to ______ such as ______.
a. external phenomena/wars b. networks/governments c. organizational attributes/firm size d. events/sponsorships
How difficult should the goals be?
a. Difficult goals yield higher output than easy to moderate goals b. Studies have shown that performance decreases when goals are set too high c. Studies have shown that easy to moderately difficult goals boost acceptance and therefore get the best results d. Both “a” and “b”