To calculate an activity’s latest finish time, you should consider its

a. predecessors’ latest finish times.
b. predecessors’ latest start times.
c. successors’ earliest start times.
d. successors’ latest start times.


d. successors’ latest start times.

Business

You might also like to view...

________ refers to incentive pay in which the wage paid is higher when a greater amount is produced.

A. Profit sharing B. Differential piece rate C. Scanlon pay D. Gainsharing E. Merit pay

Business

A Colorado ski resort opens its mountain ski trails during the summer months for the recreational enjoyment of mountain bike riders. The resort is doing which of the following?

A) using disintermediation B) using total quality management (TQM) C) using capacity management D) maintaining the core service E) using gap analysis

Business

Who was the Nigerian business professor who has been the primary voice of the Mutuality Principle?

A. Juan Manuel Elegido B. Thierry Nadisic C. John Rawls D. Michael Shaub

Business

Which of the following disconfirming responses fails to acknowledge the messages of the other person?

A. impersonal B. interrupting C. tangential D. impervious

Business