If the most optimistic time for completing an activity is 14, the most likely time is 16, and the most pessimistic time is 30, then the estimated time for the activity is ______.

a. 18
b. 19
c. 20
d. 21


a. 18

Business

You might also like to view...

Followers with the desire to exceed expectations benefit from ______.

A. directive leadership B. participative leadership C. supportive leadership D. achievement-oriented leadership

Business

During the early years of an amortizing mortgage loan, the lender applies

A) most of the monthly payment to the outstanding principal balance. B) all of the monthly payment to the outstanding principal balance. C) most of the monthly payment to interest on the loan. D) all of the monthly payment to interest on the loan. E) the monthly payment equally to interest on the loan and the outstanding principal balance.

Business

The administrative agency equivalent to a court trial is:

a. a commissioner's hearing b. a Congressional review c. a rulemaking d. an adjudicatory hearing e. none of the other choices

Business

The consultative style involves ________ behavior and is appropriate when interacting with moderate-capability employees.

What will be an ideal response?

Business