Draw the network corresponding to the following information. Also, complete the table, identify the critical path, and specify project completion time

Activity Immediate
Predecessor(s) Time
(Weeks)
A --- 3
B --- 4
C A 6
D B 9
E B 6
F C, D 6
G D, E 8
H G, F 9

Activity Earliest
Start Earliest
Finish Latest
Start Latest Finish Slack
A
B
C
D
E
F
G
H


Activity Earliest
Start Earliest
Finish Latest
Start Latest Finish Slack
A 0 3 6 9 6
B 0 4 0 4 0
C 3 9 9 15 6
D 4 13 4 13 0
E 4 10 7 13 3
F 13 19 15 21 2
G 13 21 13 21 0
H 21 30 21 30 0

Critical path is B—D—G—H, and project completion time is 30 weeks.

Business

You might also like to view...

According to Gerbner, one established difference between light and heavy viewers is that heavy viewers are ______.

A. desensitized to the impact of television B. less selective when deciding what programs to watch C. more selective when deciding what programs to watch D. less afraid of walking alone at night

Business

The marginal cost of storing and distributing digitized products–music files, for example–is practically nothing

Indicate whether the statement is true or false

Business

_____ is defined as the process of choosing a goal and developing a method or strategy to achieve that goal.

Business

When par stock is issued at a price below par, the amount below par is called a(n)

a. stated value; b. expense; c. discount; d. market value; e. dividend

Business