Slack time in a project is also known as ______________

A. project duration
B. float
C. the critical path
D. BIM


B

Trades & Technology

You might also like to view...

Green-stained brick often show no sign of a stain until they are _____ .

A. scrubbed with soap and water B. soaked in rain water C. washed in an acid solution D. exposed to salts in proprietary cleaners

Trades & Technology

On a vehicle equipped with a bladder type air bag system: The customer is concerned about the "Pass Air Bag Off" light not illuminating when their eight year old child sits in the passenger front seat. Technician A says this is normal operation. Technician B says a DTC will set for this condition. Who is correct?

A. Technician A only B. Technician B only C. Both Technician A and B D. Neither Technician A nor B

Trades & Technology

All of the following are primarily associated with public sector projects, except: (choose one)

(a) Low interest rates (b) Stocks (c) Benefits (d) Infinite life

Trades & Technology

Poodles commonly have a short hair-growth cycle

A. True B. False

Trades & Technology