Slack time in a project is also known as ______________
A. project duration
B. float
C. the critical path
D. BIM
B
You might also like to view...
Green-stained brick often show no sign of a stain until they are _____ .
A. scrubbed with soap and water B. soaked in rain water C. washed in an acid solution D. exposed to salts in proprietary cleaners
On a vehicle equipped with a bladder type air bag system: The customer is concerned about the "Pass Air Bag Off" light not illuminating when their eight year old child sits in the passenger front seat. Technician A says this is normal operation. Technician B says a DTC will set for this condition. Who is correct?