In the Blackhawk case, what role did construction schedules play in deciding the merits of the delay claim? Describe briefly how the schedules were prepared

What will be an ideal response?


"As planned" and "as built" CPM schedules were prepared after the project was
constructed. These were "after-the-fact" schedules developed by an independent -
consultant. Basing the information to be included in the schedule primarily on the
contractor's daily work logs, the consultant developed a schedule that was acceptable to
the Board of Contract Appeals. The Board acknowledged that the CPM schedule was
prepared well after events took place, but under close scrutiny of the Board, the schedule
was found to be acceptable. It is inferred, in this case, that the CPM schedule was critical
to the decision made by the Board.

Trades & Technology

You might also like to view...

Chris purchased 500 milliliters of medication. How many cubic centimeters did he purchase?

What will be an ideal response?

Trades & Technology

Emus can run at speeds of up to _____ miles per hour.

Fill in the blank(s) with the appropriate word(s).

Trades & Technology

The part of the tire that is just under the tread of a radial tire is called the ________

A) Body (carcass) ply B) Bead C) Inner liner D) Belt

Trades & Technology

In what two regions/countries are ducks and geese a major part of the overall diet?

A. United States and Mexico B. Spain and Italy C. China and Southeast Asia D. Japan and India

Trades & Technology