If the most optimistic time for completing an activity is 6, the most likely time is 9, and the most pessimistic time is 14, then the estimated time for the activity is ______.
A. 9.33
B. 11.63
C. 12.38
D. 9.54
A. 9.33
You might also like to view...
A defendant who believes that he or she has been injured by the plaintiff can file a(n) ________ against the plaintiff.
A. writ of habeas corpus B. interpleader C. cross-complaint D. writ of certiorari
In a company where units are given autonomy to work independently, but are now asked to work together, the units may become territorial and refuse to share ideas for fear of being eliminated. This functional structure will produce which drawback?
A. Redundancy across units B. Cascading effect of errors C. Low levels of centralization D. Self-cannibalization E. Inability to support cost competency
This element of the planning and source of power in a negotiation is especially important because this is the option that likely will be chosen should an agreement not be reached.
A. None of these options is correct. B. BATAN C. BATNA D. BANTA
A sight draft that arises when a seller extends credit to a buyer with the sale of goods is known as a ________
A) check B) time draft C) trade acceptance D) demand draft