Suppose you have the following project digraph. (The numbers in parentheses represent hours.)
If we use decreasing-time algorithm to schedule this project with two processors, we should start by assigning
A. task B to one processor, task E to the other one.
B. task A to one processor, task C to the other one.
C. task A to one processor, task B to the other one.
D. task B to one processor, task C to the other one.
E. none of these
Answer: B