A manager assigns a worker a project to be completed and then holds periodic meetings

with the worker to determine whether target dates for subparts of the project are being met.
Which management function do these meetings represent?



a. Planning
b. Organizing
c. Leading
d. Controlling
e. Leadership


D

Trades & Technology

You might also like to view...

A machine in the JLM packaging plant is used to fill individual-serving coffee brewing containers with 9.4 g of coffee. The average actual weight of the coffee in each container is found to be 9.50 g with a standard deviation of 0.05 g. If a batch run consists of 250 000 containers, how many containers in a batch can be expected to weigh less than 9.4 g?

What will be an ideal response?

Trades & Technology

Which piece of equipment shears off sections of soil and flips them over?

a. chisel plow c. cultivator b. moldboard plow d. disk plow

Trades & Technology

The ____ was once widely used to compare electrical charges and served as a crude voltmeter.

a. lightning arrester b. electroscope c. generator d. conductor

Trades & Technology

What is an MSDS?

What will be an ideal response?

Trades & Technology