If t is the expected completion time for a given activity, then:

A) LF = LS - t.
B) EF = ES - t.
C) EF = ES + t.
D) EF = LS - t.


Answer: C

Business

You might also like to view...

The union would like to negotiate with management. However, management sent Brian as their representative. The union would prefer to work with Raghib. Therefore, the union is refusing to negotiate until management allows Raghib to be its representative. The union is likely in violation of the ______.

A. Railway Labor Act of 1926 B. National Labor Relations Act of 1935 (Wagner Act) C. Labor Management Relations Act of 1947 (Taft-Hartley Act) D. Labor Management Reporting Disclosure Act of 1959

Business

Once accepted, the trademark is published in the Trademark Official Gazette to allow any party ________ days to oppose or request an extension to oppose the use of the mark. 

A. 90 B. 30 C. 10 D. 180

Business

There is considerable overlap in the scientific method and management science techniques. Which of the following steps is shared between them?

A) observation B) problem definition C) model construction D) implementation

Business

The National Labor Relations Board supervises all elections for union representation

Indicate whether the statement is true or false

Business