Name five conditions under which a task becomes critical.

What will be an ideal response?


1. The task has 0 slack.
2. The task has a Must Start On or Must Finish On date constraint.
3. The task has an As Late As Possible constraint in a project scheduled from a Start date.
4. The task has an As Soon As Possible constraint in a project scheduled from a Finish date.
5. The task has a scheduled Finish date that is the same or beyond its deadline date. (A deadline date doesn't constrain a task, but it does provide a visual indicator if a scheduled Finish date slips beyond the deadline date.)

Computer Science & Information Technology

You might also like to view...

When a program requires input to contain a minimum number of characters, the string __________ function can be used to check that the input is valid.

Fill in the blank(s) with the appropriate word(s).

Computer Science & Information Technology

If you place conditions in different Criteria rows in the design grid, all of the conditions must be met to select a record.

Answer the following statement true (T) or false (F)

Computer Science & Information Technology

An air filter mask sometimes used by a computer or network technician is a type of breathing tank

Indicate whether the statement is true or false

Computer Science & Information Technology

A ________ is a small device with a display that has a number that changes frequently.

A. one-time-password token B. magnetic stripe card C. USB token D. smart card

Computer Science & Information Technology