Name five conditions under which a task becomes critical.
What will be an ideal response?
1. The task has 0 slack.
2. The task has a Must Start On or Must Finish On date constraint.
3. The task has an As Late As Possible constraint in a project scheduled from a Start date.
4. The task has an As Soon As Possible constraint in a project scheduled from a Finish date.
5. The task has a scheduled Finish date that is the same or beyond its deadline date. (A deadline date doesn't constrain a task, but it does provide a visual indicator if a scheduled Finish date slips beyond the deadline date.)
You might also like to view...
When a program requires input to contain a minimum number of characters, the string __________ function can be used to check that the input is valid.
Fill in the blank(s) with the appropriate word(s).
If you place conditions in different Criteria rows in the design grid, all of the conditions must be met to select a record.
Answer the following statement true (T) or false (F)
An air filter mask sometimes used by a computer or network technician is a type of breathing tank
Indicate whether the statement is true or false
A ________ is a small device with a display that has a number that changes frequently.
A. one-time-password token B. magnetic stripe card C. USB token D. smart card