The correct order of application for a roof installation at an eave is _____
a. underlayment, starter strip, finish roof material, and drip edge flashing
b. starter strip, drip edge flashing, underlayment, and finish roof material
c. drip edge flashing, starter strip, underlayment, and finish roof material
d. drip edge flashing, underlayment, starter strip, and finish roof material
d
You might also like to view...
What is the highest gauge pressure that an acetylene regulator should be set at?
A. 5 psi (35 kPa) B. 15 psi (100 kPa) C. 25 psi (175 kPa) D. 100 psi (300 kPa)
The ____ was once widely used to compare electrical charges and served as a crude voltmeter.
a. lightning arrester b. electroscope c. generator d. conductor
A(n) ____ print is used as a guide for assembling finished parts.
A. scale B. build C. working D. assembly
The pilot of a remotely piloted aircraft shall give way to manned aircraft . . . . .
A. at the request of the pilot of the manned aircraft. B. when the manned aircraft is higher in altitude than the remotely piloted aircraft. C. when the manned aircraft is lower in altitude than the remotely piloted aircraft. D. at all times.