Describe and rank any three decision rules for terminating an ongoing project before completion

What will be an ideal response?


Answers will vary with students' rankings. The decision rules listed in the text include the following:
When cost exceeds business benefits.
When the project no longer meets strategic fit criteria.
When deadlines continue to be missed.
When technology evolves beyond the project's scope.
The latter may not be a concern in many situations; evolution of technology probably hasn't cancelled a home construction project for a while. Costs exceeding benefits may be critical for smaller firms and extremely large corporations may be less sensitive to cost issues.

Business

You might also like to view...

____________________ is the practice of using the least optimistic estimate when two estimates of amounts are about equally likely

Fill in the blank(s) with correct word

Business

Mark and his brother, Rick, each own farms. Rick is experiencing severe financial difficulties and cannot afford to buy feed for his cattle. Mark purchases $2,000 of feed and gives Rick one-half of the feed. Mark tells Rick that there is no need to repay him and to consider the feed a gift. Which of the following statements is true?

A. Mark can deduct $2,000 for the feed. B. Rick must report $1,000 as income. C. Mark can deduct $1,000 for the feed. D. None of the above is true.

Business

All factors in a future value table must be less than or equal to 1.000

Indicate whether the statement is true or false

Business

Sales resistance is a natural response that tends to provide the salesperson with valuable information about the consumer

Indicate whether the statement is true or false

Business