The overall project risk factor is known to be 0.5. The probability of dependency failure is twice the probability of complexity failure and four times the probability of maturity failure
The consequence of performance failure is twice the consequence of reliability failure, four times the consequence of schedule failure and eight times the consequence of cost failure. What is the difference between the probability of maturity failure and the consequence of cost failure?
Maturity X Cost Y
Complexity 2X Schedule 2Y
Dependency 4X Reliability 4Y
Performance 8Y
A) 0.026
B) 0.033
C) 0.041
D) 0.048
A
You might also like to view...
Which of the following is a true statement about Title VII of the Civil Rights Act of 1964?
A. The act is enforced by the U.S. Department of Labor B. The act applies to organizations with 15 employees or more C. The act prohibits employers from discriminating against workers due to their age D. The act protects employers from employee threats E. The act banned affirmative action in organizations
Fair market value for purposes of eminent domain: A)?Is the value immediately after the announcement of the taking
B)?Is the value immediately before the announcement of the taking. C)?What a willing buyer would pay a willing seller. D)?Is determined by the property tax valuations.
Script-level variables have ________ duration
a) local b) global c) automatic d) static
How are employers protected under the Act from being pressured to enter prehire agreements with minority unions?