A project has the precedence requirements and activity durations shown in the table. After he draws the network, the project manager decides to represent a few activities by a hammock activity
Which is a legitimate hammock activity for this project?
Time Predecessor
A 7
B 8 A
C 13 A
D 8 A
E 7 B
F 6 C
G 6 D
H 11 E
I 12 G
J 14 H, F, I
A) Combine activities A, B, C
B) Combine activities B, E, H
C) Combine activities E, F
D) Combine activities G, H, I
B
You might also like to view...
Strategic and tactical decisions in a customer-oriented organization should be made:
A) cross-functionally and cross-divisionally. B) by the marketing department. C) by the services department. D) by the customer relations department.
If an employer has been approved for a voluntary protection program, then the employer's company is not inspected for three years.
Answer the following statement true (T) or false (F)
Postoptimality analysis is most closely associated with
A) collecting input data. B) developing a model. C) sensitivity analysis. D) writing a computer program. E) None of the above
Enterprise resource planning applications span the supplier, customer, and internal supply chain areas
Indicate whether the statement is true or false.