If a project is expected to be completed in 68 days with a project variance of 9 days, what is the probability that the project will be completed within 50 days?

a. 0%
b. between 5% and 10%
c. between 15% and 30%
d. over 35%


a. 0%

Business

You might also like to view...

The current ratio is a

a. liquidity ratio. b. profitability ratio. c. long-term solvency ratio. d. market strength ratio.

Business

What are the major media formats available to marketers? What are the strengths and weaknesses of each format?

What will be an ideal response?

Business

The Restatement of the Law of Contracts summarizes contract principles as set out by the U.S. Supreme Court

Indicate whether the statement is true or false

Business

Reliance Corporation sold 4,000 units of its product at a price of $15 per unit. Total variable cost per unit is $8.50, consisting of $7.75 in variable production cost and $0.75 in variable selling and administrative cost. Compute the contribution margin for the company.

A. $26,000 B. $31,000 C. $34,000 D. $36,900 E. $60,000

Business