An undesirable schedule variance always indicates that the project is running behind schedule.
Answer the following statement true (T) or false (F)
False
A negative schedule variance suggests problems or changes that have taken place. Schedule variance measures progress in dollars rather than time units. Therefore, it is unlikely that any translation of dollars to time will yield accurate information telling if any milestone or critical path is early, on-time, or late.
You might also like to view...
During the initial planning phase of an audit, a CPA most likely would:
A. discuss the timing of the audit procedures with the client's management. B. inquire of the client's attorney as to any unrecorded claims. C. identify specific internal control activities that are likely to prevent fraud. D. evaluate the reasonableness of the client's accounting estimates.
Stock X has the following data. Assuming the stock market is efficient and the stock is in equilibrium, which of the following statements is CORRECT? Expected dividend, D1$3.00 Current Price, P0$50 Expected constant growth rate6.0%
A. The stock's expected dividend yield and growth rate are equal. B. The stock's expected dividend yield is 5%. C. The stock's expected capital gains yield is 5%. D. The stock's expected price 10 years from now is $100.00. E. The stock's required return is 10%.
Manufacturers generally prefer?
a. Product differentiation b. Product standardization c. Neither product differentiation nor product standardization d. The preferences of manufacturers are impossible to assess
Present Value of 1Periods3%4%5%6%7%8%9%10%12%30.91510.88900.86380.83960.81630.79380.77220.75130.711840.88850.85480.82270.79210.76290.73500.70840.68300.635550.86260.82190.78350.74730.71300.68060.64990.62090.567460.83750.79030.74620.70500.66630.63020.59630.56450.506670.81310.75990.71070.66510.62270.58350.54700.51320.452380.78940.73070.67680.62740.58200.54030.50190.46650.403990.76640.70260.64460.59190.54390.50020.46040.42410.3606100.74410.67560.61390.55840.50830.46320.42240.38550.3220Future Value of
1Periods3%4%5%6%7%8%9%10%12%31.09271.12491.15761.19101.22501.25971.29501.33101.404941.12551.16991.21551.26251.31081.36051.41161.46411.573551.15931.21671.27631.33821.40261.46931.53861.61051.762361.19411.26531.34011.41851.50071.58691.67711.77161.973871.22991.31591.40711.50361.60581.71381.82801.94872.210781.26681.36861.47751.59381.71821.85091.99262.14362.476091.30481.42331.55131.68951.83851.99902.17192.35792.7731101.34391.48021.62891.79081.96722.15892.36742.59373.1058Present Value of an Annuity of 1Periods3%4%5%6%7%8%9%10%12%32.82862.77512.72322.67302.62432.57712.53132.48692.401843.71713.62993.54603.46513.38723.31213.23973.16993.037354.57974.45184.32954.21244.10023.99273.88973.79083.604865.41725.24215.07574.91734.76654.62294.48594.35534.111476.23036.00215.78645.58245.38935.20645.03304.86844.563887.01976.73276.46326.20985.97135.74665.53485.33494.967697.78617.43537.10786.80176.51526.24695.99525.79505.3282108.53028.11097.72177.36017.02366.71016.41776.14465.6502Future Value of an Annuity of 1Periods3%4%5%6%7%8%9%10%12%33.09093.12163.15253.18363.21493.24643.27813.31003.374444.18364.24654.31014.37464.43994.50614.57314.64104.779355.30915.41635.52565.63715.75075.86665.98476.10516.352866.46846.63306.80196.97537.15337.33597.52337.71568.115277.66257.89838.14208.39388.65408.92289.20049.487210.089088.89239.21429.54919.897510.259810.636611.028511.435912.2997910.159110.582811.026611.491311.978012.487613.021013.579514.77571011.463912.006112.577913.180813.816414.486615.192915.937417.5487An individual is planning to set-up an education fund for his grandchildren. He plans to invest $10,000 annually at the end of each year. He expects to withdraw money from the fund at the end of 10 years and expects to earn an annual return of 8%. What will be the total value of the fund at the end of 10 years? (PV of $1, FV of $1, PVA of $1, and FVA of $1) (Use appropriate factor(s) from the tables provided.) A. $67,107 B. $215,890 C. $100,000 D. $144,866 E. $46,320