Which of the following statements regarding critical paths is true?

A) The shortest of all paths through the network is the critical path.
B) Some activities on the critical path may have slack.
C) Every network has only one critical path.
D) On a specific project, there can be multiple critical paths, all with exactly the same duration.
E) The duration of the critical path is the average duration of all paths in the project network.


D

Business

You might also like to view...

Countervailing duties may be imposed

a. in response to a foreign export subsidy. b. in response to a foreign antidumping tariff. c. to promote exports of domestic companies. d. to promote imports of domestic consumers.

Business

Misstatements that are detected, but individually are not material, should be ignored when determining the appropriate audit report

a. True b. False Indicate whether the statement is true or false

Business

Raj, a senior engineer at a manufacturing firm, leads a designing team from the home country, while the team works from the host country. Currently, the team is working on a project and is in the verge of finalizing a design. At this point, the client communicates a change in the design. Raj has to pass this information to his team immediately. In this scenario, which of the following will be the

ideal channel of communication?? A) ?Kinesic communication B) ?The telephone C) ?A face-to-face meeting D) ?Metacommunication

Business

The collective bargaining process may include activities such as strikes and boycotts.

Answer the following statement true (T) or false (F)

Business