Shortening an activity's duration is termed crashing.

Answer the following statement true (T) or false (F)


True

Crashing is a term that has emerged in the project management lexicon for shortening the duration of an activity of project beyond when it can normally be done.

Business

You might also like to view...

Those leaders who have no official authority, but do have the ability to influence others are:

a. formal leaders. b. authoritarian leaders. c. participatory leaders. d. informal leaders.

Business

When communicating with people in other countries, it is useful to use figures of speech and clichés as they are understood universally

Indicate whether the statement is true or false

Business

Using the information below, compute the raw materials inventory turnover:     Raw materials used$121,600 Beginning raw materials inventory 18,000 Ending raw materials inventory 20,200 

A. 6.37. B. 6.02. C. 54.0. D. 60.6. E. 6.76.

Business

Which of the following formulas is the right formula for calculating contribution margin ratio?

A) Contribution margin ratio = Contribution margin + Net sales revenue B) Contribution margin ratio = Contribution margin / Net sales revenue C) Contribution margin ratio = Contribution margin x Net sales revenue D) Contribution margin ratio = Contribution margin - Net sales revenue

Business