It is calculated that a house requires 18,500 brick to complete its brick veneer facade. The contractor's experience indicates that it takes 4% more than the calculated amount to complete. If 4% more bricks are needed, how many more bricks than the 18,500 will it take to complete the job?
What will be an ideal response?
740
You might also like to view...
____ panels are used in applications in which they will be briefly exposed to the elements during construction before being permanently protected.
A. Exposure 1 B. Exposure 2 C. Exterior D. Interior
What component of a boiler consists of valves, fittings, piping, and connections suitable for the pressure of the steam being transported?
A. Burners B. Boiler feedwater system C. Economizer D. Steam distribution system
Volunteering is a good way to feel connected to your community. Volunteering could also help develop communication, management, or supervisory skills that you may not develop by just attending school.
a. True b. False
A channel iron crossmember weighs 3 1/4 pounds per foot. What is the weight in pounds of three crossmembers, each 1 1/2 feet long?
A. 13 1/8 B. 14 5/8 C. 15 1/4 D. 16 1/2