Answer the following statements true (T) or false (F)

1. One of the characteristics of the inbound supply chain for many projects is that it is short.
2. Doing a root cause analysis of why a project failed is one of the four fundamental steps needed to create and manage a project supply chain.
3. Potential benefits of the project to the company is included in calculating earned value.
4. Schedule efficiency refers to how closely the project’s progress is tracking relative to its original plan.
5. The need for more face-to-face meetings is an implication resulting from the increasingly global nature of projects and project teams.


1. False
2. False
3. False
4. True
5. False

Business

You might also like to view...

The ISO promotes standardization with a view of facilitating the international exchange of goods and services

Indicate whether the statement is true or false

Business

A defendant who has not been negligent but who is made to pay a strict liability judgment can bring a separate action against the negligent party in the chain of distribution to recover its losses.

Answer the following statement true (T) or false (F)

Business

Under the indirect method of determining cash flows from operations, which of the following is added to net income?

a. An increase in Accounts Receivable b. A decrease in Income Taxes Payable c. A decrease in Inventory d. An increase in Prepaid Expenses

Business

Indirect costs, such as manufacturing overhead, are variable costs.

Answer the following statement true (T) or false (F)