Suppose you have the following project digraph. (The numbers in parentheses represent hours.)
Consider the following timeline using two processors.

A. This timeline is an optimal schedule.
B. This is the timeline one gets using the critical-path algorithm.
C. This is the timeline one gets using the decreasing-time algorithm.
D. This timeline is an illegal schedule.
E. none of these


Answer: C