A project has the activity duration and cost information indicated in the table where all times are in weeks

What is the total cost for completing this project in 40 days?

Activity Predecessor Normal Time Normal Cost Crash Time Crash Cost
A -- 8 $12,000 5 $22,000
B A 12 $18,000 9 $32,000
C A 15 $22,000 9 $62,000
D B 3 $9,000 2 $18,000
E C 9 $15,000 5 $35,000
F E 7 $5,000 5 $8,000
G D 8 $13,000 6 $23,000
H A 12 $20,000 8 $32,000
J H 6 $45,000 4 $56,000
A) $172,000
B) $218,000
C) $192,000
D) $159,000


A

Business

You might also like to view...

The temperature in the room should be slightly cool rather than slightly warm

a. true b. false

Business

Both the table-level and column-level approaches to creating a constraint can be included in the same command. _________________________

Indicate whether the statement is true or false

Business

Performing the risk analysis is part of Core Process 2, (Plan and monitor the project)

a. True b. False Indicate whether the statement is true or false

Business

A member's portion of a consolidated NOL may be carried back against that member's taxable income from the preceding two separate return years.

Answer the following statement true (T) or false (F)

Business