Activities A and B have a finish to finish relationship and early start and finish times as shown. What is the result of incorporating a 4-day lag between activities C and B?
A) The early finish for A increases to 31.
B) The early start time for A increases to 24.
C) The early finish time for B increases to 31.
D) The early start time for D falls to 23.
C
You might also like to view...
When delivering a speech that focuses on a process or procedure, you will probably find it most useful to arrange your ideas in either ______ or ______ order.
a. topical; spatial b. spatial; chronological c. cause and effect; topical d. chronological; topical
Answer the following statements true (T) or false (F)
The criteria for capitalizing a real estate lease are identical to those of other leases.
Using unbiased and neutral language helps to promote fairness and makes no assumptions about any group of people
Indicate whether the statement is true or false
Joe's Camera shop has a favorite model that has annual sales of 145. The cost to place an order to replenish inventory is $25 per order, and annual inventory holding cost per unit is $20. Assume the store is open 350 days per year
a. What is the optimal order size? b. What is the optimal number of orders per year? c. What is the optimal number of days between orders? d. What is the annual holding and setup cost?