The items shown in the accompanying figure are assorted ____ types.
A. table
B. column
C. chart
D. graphic
Answer: C
You might also like to view...
d. Boolean
a. Float b. Array c. Object d. Boolean
The first element of a ________ is the new field name that will display the calculated value
Fill in the blank(s) with correct word
A group of related tables is called a(n) ________ database
Fill in the blank(s) with correct word
Match the following terms to their meanings:
I. Subtask II. Resource Sheet view III. Effort-driven scheduling IV. Crashing V. Leveling A. Related tasks that further define the summary tasks B. A process of correcting overallocated resources C. Adding additional resources to a project D. Formatted in columns and rows E. When the duration of a task is shortened as resources are added or lengthened as resources are removed