Optimistic time refers to:

A) the maximum period of time for an activity to be completed.
B) the minimum period of time for an activity to be completed.
C) the planner's "best guess" of the amount of time the activity actually will require for completion.
D) the maximum period of time for an entire project to be completed.
E) the average period of time for an activity to be completed.


B
Explanation: B) The minimum time that it takes for an activity to be completed is optimistic time.

Business

You might also like to view...

A mentor has nothing to do with building your network, they focus on the inner-self only.

a. True b. False

Business

Which of the following is NOT an example of dependent demand items?

A) shoelaces, shoes B) wheels, car C) carafes, coffeemakers D) ice skates, roller skates

Business

To transfer contract rights to a third party is:

a. assignment b. delegation c. repudiation d. beneficiary e. none of the other choices

Business

Which of the following is commonly chosen as an executor?

A) An attorney B) A family member C) A bank trust company employee D) All of the above

Business