When using project management software, what are six factors that drive the calculation of time?

What will be an ideal response?


Six factors that drive the calculation of time include start time of the project, task durations, project calendars, task dependencies, task constraints and deadlines, and resource assignments and task types.

Business

You might also like to view...

The macro dimensions of the environment are economic, social and cultural, political and legal, and technological

Indicate whether the statement is true or false

Business

Universally desirable leadership attributes do not include ______.

A. effective bargainer B. dictatorial C. plans ahead D. win-win problem solver

Business

A local firm that takes MRIs for patients, and sends several people to various hospitals and doctors offices to inform them about their service is using:

a. trade salespeople b. technical salespeople c. direct order takers d. order getters e. missionary salespeople

Business

Liversuch Industries uses a kanban system to manage production of the J-15 subassembly

They have an hourly demand for 250 units and use containers that can hold 50 units each. It takes 90 minutes to fill and move a container of parts to the right place on the J-15 line that is currently rated at a 20% safety factor. How many production cards are needed? A) 540 B) 100 C) 9 D) 1.5

Business