The owner is required to provide payment bond to the GC whose bid has been accepted
A) at the time of executing the owner-GC agreement.
B) when the owner gives the notice to GC to proceed with the work.
C) when the GC provides performance bond to the owner.
D) within one week of the GC commencing construction.
E) none of the above.
E) none of the above.