The time estimate that represents the time to complete the activity if everything goes wrong is the?

a. Optimistic completion time
b. Most likely completion time
c. Pessimistic completion time
d. Least likely completion time


c. Pessimistic completion time

Business

You might also like to view...

Transfer pricing is a term that applies to transactions between different divisions or units of the same company

Indicate whether the statement is true or false

Business

Powell Motors, an engine manufacturer, forms a team that is led by Jacob to design and develop a new jet engine. Jacob, after setting the objectives and benchmarks, assigns clearly-defined tasks to his teammates to achieve the desired goal. In the context of the role of a leader in the team concept, it is evident that Jacob facilitates the work of the team to accomplish ________.

A. accountability B. partnering C. infrastructure D. learning

Business

State courts are independent of federal courts.

Answer the following statement true (T) or false (F)

Business

From a behavioral perspective, the anomaly known as post-earnings announcement drift or momentum is best explained by

A) self attribution bias. B) loss aversion. C) representativeness. D) familiarity bias.

Business