What are two tactics that seek to protect the owner against future claims by unpaid subcontractors or suppliers?

What will be an ideal response?


Some contracts require the contractor to give the owner assurance or proof
that the prime has paid its subcontractors and suppliers when payment
applications are made. Alternatively, contracts may require the prime
contractor to demand lien waivers from the subcontractors as a condition
for payment, in which the subcontractor gives up its right to a mechanic’s
lien for the work covered in the progress payment

Trades & Technology

You might also like to view...

Using the modified X-method of tire rotation on a front wheel drive vehicle, where should the left front wheel be placed?

A) Right rear B) Keep it at the left front C) Left rear D) Right front

Trades & Technology

Which of the following is NOT a Bluetooth error correction scheme?

A. 1/3 rate FEC B. 2/3 rate FEC C. ARQ D. CRC

Trades & Technology

The subsequent problems deal with the circuit below containing complex impedances.If Z1=0?, Z2=??, and Z3=10?, what is the equivalent impedance of the circuit?

A. ? ? B. 1/10 ? C. 0 ? D. 10 ? E. (? + 10) ?

Trades & Technology

Two technicians are discussing how torque is increased inside a manual transmission/transaxle. Technician A says that the gear ratio in first gear between the main shaft and the countershaft should be multiplied by the ratio of the corresponding countershaft gear and output shaft gear. Technician B says that the two ratios should be added together. Which technician is correct?

A) Technician A only B) Technician B only C) Both technicians A and B D) Neither technician A nor B

Trades & Technology