Jessica just received the following information on her project: PV = 200, EV = 300, AC = 250, BAC = 1500, EAC = 1208. In terms of cost at completion

A. The project will currently finish behind schedule.
B. There is insufficient information to draw conclusions.
C. The project will currently finish over budget.
D. The project will currently finish under budget.
E. The project will currently finish on budget.


Answer: D

Business

You might also like to view...

Which of the following statements about the Calvin cycle is correct?

A. The CO2 is absorbed and reduced to C2H2O2. B. The CO2 is absorbed and reduced to CH2O. C. The CO2 is absorbed and used to form ATP. D. The CO- is absorbed and reduced to CH2O.

Business

Which of the following is an adequate reason for choosing passive voice?

a. To emphasize the "you" focus b. To avoid assessing blame c. To make the sentence more emphatic d. To make the sentence more descriptive

Business

Which of the following is a false statement about matrix structure?

A. Employees are permanently transferred from a functional area to the project area. B. Employees' jobs may be split several ways. C Matrix structure helps organizations maximize the utilization of their resources. D. Employees may have two superiors.

Business

Billy is the star of his school’s football team. He will not go out onto the field without his lucky sweatbands. He thinks that he cannot run as fast without them. Billy’s decision to play the game is based on which error?

a. Framing b. Uncertainty c. Randomness d. Lack of participation error

Business