If your project has spent $50,000 versus a budget of $45,000 and it is a week ahead of schedule, is it a certainty that your project is doing well? Explain why or why not.
Fill in the blank(s) with the appropriate word(s).
Answer will vary
Not necessarily. You need more information to draw that conclusion. You do not know what work has been accomplished for the money spent.
You might also like to view...
Adult humans cannot synthesize ________ out of the ________ common amino acids.
A. nine; twenty B. half; all C. eleven; twenty D. any; twenty E. nine; eleven
Discuss the importance of working capital management and how it relates to the working capital cycle of a small business.
What will be an ideal response?
The effective interest rate on bonds is lower than the stated rate when bonds sell
a. above face value. b. at maturity value. c. below face value. d. at face value.
The probability that Pete will catch fish when he goes fishing is .88. Pete is going to fish 3 days next week. Define the random variable x to be the number of days Pete catches fish. The probability that Pete will catch fish on exactly one day is
A. 0.880. B. 0.038. C. 0.040. D. 0.960.