What distinguishes the last periodic payment from the final payment made to the contractor on most construction projects?
What will be an ideal response?
The last periodic payment is made after a project has reached substantial
completion. After the last periodic payment is made, the owner still will be withholding
the retainage. The retainage, often as much as 10% of the contract amount, is released at
the point of final completion in the form of the final payment. The punch list typically
separates the last periodic payment and the final payment.
You might also like to view...
By dividing the ____ rating of a lamp by the watts rating, a value called the efficacy of the lamp is determined.
A. volt B. lumen C. ampere D. color
Technician A says that an air-fuel mixture that is too lean can cause burned internal engine parts. Technician B says an overly rich mixture can cause oil wash from cylinder walls. Which technician is correct?
A. Technician A B. Technician B C. Both technicians D. Neither technician
The _______ is the family history of a pup and will list any titles earned by its ancestors
Fill in the blank(s) with correct word
The "brain" of the computer is the ________
A) RAM B) PROM C) CPU D) AD converter